Week 1:
The web team completed putting the mentors’ information and the calendar on the website. The chassis with wheels, transmission and the arc was also drawn in CAD. The design team also completed sketches of the guide line conveyer belt and ordered the parts necessary for the completion of the robot. Mechanic team built the chassis together.
 
Week 2:
The program team got C++ to work. The design team made a list of parts for the guide and finished the prototype of the drum. Electrical team hooked up the camera and attached battery’s and fixed speed controllers and got robot to drive. The web team was able to upload mentor pictures and a new banner on the website. The mechanical team finished assembling the transmissions. The writing team started composing the Chairman’s Report submission.


Week 3:
The sprockets and chains were adjusted and fixed on the prototype of the robot. Web team outlined an initial redesign concept in Photoshop.  Wheels were put on the robot by the mechanics team while they kept working on other areas to improve the robot’s design.